Street & Road Construction Projects

Leprino Public Improvements

Role: Prime Contractor
Owner: Leprino Food Company
Contract Amount: $1,930,283
Construction Dates: 7/11-12/11
Description: Complete removal and reconstruction of approximately ¾ mile of City roadway and Highway 85 intersection paving and signalization improvements including: Over 4000 SY of 12” concrete paving and over 12,000SY of asphalt paving; 5000LF of curb and gutter; storm sewer improvements; sanitary sewer rehabilitation; and landscaping.

Evans 31st St. Reconstruction

Role: Prime Contractor
Owner: City of Evans
Contract Amount: $1,453,857
Description: Complete removal and reconstruction of approximately ¾ mile of City arterial including: 700 LF of 43” X 60” HERCP storm pipe, 10 inlet structures, 15,000 SY of asphalt paving, 4,500 LF of curb and gutter, 100 LF of 54” steel casing bore under UP Railroad, construction of a slip ramp onto HWY 85.

59th Ave. Reconstruction

Role: Prime Contractor
Owner: City of Greeley
Contract Amount: $1,235,320
Construction Dates: 6/08-11-08
Description: Widening and reconstructing three-quarters of a mile of City of Greeley arterial, including embankment, stone-strong precast concrete block wall, curb, gutter, sidewalk, base course, and paving.

Hwy 392 & I-25 Interchange Improvements

Role: Prime Contractor
Owner: Colorado Department of Transportation
Contract Amount: $1,100,000
Construction Completion Date: 9/07
Description: Reconstruct of I-25 off ramps, widening, re-signalization, and overlay of Hwy 392 bridge deck and approaches.