Ken Mitchell Lakes Pump Station

ken-mitchell-lakes-pump-stationRole: Prime Contractor
Owner: City of Brighton
Contract Amount: $1,117,720
Construction Dates: 11/08-8/09
Description: Construct two concrete cast-in-place wet well structures 30 feet below grade. Dewater site for construction of wet wells bringing groundwater table down 22 ft within 100 feet of the South Platte River. Install sheet piling in the river to allow for construction of a concrete inlet/outlet structure. Install submersible pumps in wet well structure and perform site road construction and maintenance.