Site Demolition Projects

Old Larimer County Fairgrounds

Role: Prime Contractor
Owner: City of Loveland Parks Department
Contract Amount: $131,000
Construction Dates: 7/07
Description: Abandonment of wet services, demolition of building slabs, foundations, CMU structures, and cast-in-place grandstand structure. Onsite crushing of demolished concrete materials to meet class 6 base course specifications.

Founders Parkway

Role: Sub-contractor
Owner: Colorado Department of Transportation, c/o Castle Rock Construction Company LLC
Contract Amount: $105,375
Construction Completion Date: 8/11
Description: Crush 38,000 SY of 8” concrete pavement and 10,000 LF of curb and gutter ongrade to Class 1 Road Base and windrowed in place. Crushed material was blended into subgrade materials improving the R value from 8 to 42. Crushing in place eliminated over 22,000 tons of exported removals and 40,000 tons of imported subgrade material for the project.

West Bates Demolition

Role: Sub-contractor
Owner: Colorado Department of Transportation, c/o Castle Rock Construction Company LLC
Contract Amount: $222,000
Construction Completion Date: ongoing
Description: Crush 40,000 tons of concrete and asphalt pavement and complete demolition of 10 acre steel foundry site. Crushed materials are being recycled and used as roadway base course, stabilization rock, temporary surfacing and concrete rock.