Streetscape Projects

Oak Street Plaza

Role: Prime Contractor
Owner: City of Fort Collins Parks Department
Contract Amount: $1,098,522
Construction Dates: 3/06-8/06
Description: Refurbish Oak Street Plaza, including: demolition of existing plaza paving, furnishing and installing water feature (design by Aqua Engineering), structural concrete retaining walls, concrete stairs and flatwork, curb and gutter, utility tie-ins, lithocrete paving, granite and concrete unit pavers, bus shelter, custom pole lighting, custom handrail and fencing.

Downtown Alley Enhancements

Role: Prime Contractor
Owner: Fort Collins Downtown Development Authority
Contract Amount: $1,595,306
Construction Dates: 7/10-11/10
Description: Removal and reconstruction of two alleys covering 24,000 SF in downtown Fort Collins including: demolition, concrete flatwork, interlocking pavers, electrical and lighting, site amenities, storm sewer installation.

Hildebrand Ranch Open Space

Role: Prime Contractor
Owner: Jefferson County Open Space
Contract Amount: $309,675
Construction Dates: 9/09-12/09
Description: Installation of a 31,000 SF permeable paver parking lot including gravel under drain system, barrier rocks, permeable pavers, concrete curb gutter and walk.